Friday 9 July 2010

Frustrated....

So I have to admit that when we took this on, despite having watched lots of Grand Designs (back when we had a TV) and realising that things take longer and go over budget I thought it would probably run to schedule and not be too bad - I should have paid more attention to Grand Designs!

Currently I am feeling a little bit frustrated with the whole thing - whilst there is progress every week - it often feels like it was just a bit more insulation each time (which I am sure the builders would agree with!). And the windows are still a saga - after having been ordered eventually, there is now a possibility that it will be 10 weeks - which is another 8 from now, which puts us mid-september before we move in. Hopefully it won't be that long, but we have ended up in the summer, and therefore coinciding with factory fortnight (factories closing for 2 weeks) which if it happens in this factory will definately delay things.

The progress update this week (there has been some) is that all the insulation and first fix of electrics and plumbing is done upstairs and plasterboarding the whole area has begun. Also the first bit of wall insulation has begun downstairs, after long discussions of how to minimally fix the studwork to the brickwork to avoid cold bridging (builder Chris coming up with the final solution, an extra horizontal piece on the studwork which then only needs 3 or 4 attachments to the brickwork). This means that the solar boys can come back next week to put in all the pipework and the tank, and after that the heat recovery system should go in. We are getting upstairs plastered next week, and the upstairs floor delivered for it to sit for a while and acclimatise before being put in. All this is happening without windows, so we have to hope that the openings are weather tight!?

Whats left still to do: all the insulation downstairs, insulation in the roof, first fix downstairs, staircase, heat recovery system to go in, solar to be sorted, second fix everywhere and windows. Decorating and downstairs floor and any storage will be us apart from tiling in the shower which we think will be better executed around the fittings if the builders do it!
Ready for the second fix we have chosen all our sanitaryware - so hopefully the plumber is ordering the right stuff and there won't be a delay! We are in disucssion with each other about how much extra to get for the kitchen. All we have so far is the double sink unit and aluminium dresser. We have decided which induction hob we would like, and are just working out about a unit to put that in, and what we do about fridge, freezer, cooker, island, etc. We think we have decided on a unit and worktop for the hob, and will probably get that and a decent fridge and freezer before or almost as soon as we move in, and then work up to the other units and cooker once we know if we have any money left (or have earnt some more). We are negotiating about the extractor fan - Emily has done some excellent research finding really quiet, efficient, expensive hoods so we haven't quite agreed on which one yet!

I guess things are progressing - and 8 weeks from now isn't that long - its just that when we move in it will be 12 months after we bought the place, 18 months after we moved to Nottingham, and 32 months after our stuff went into storage!

2 comments:

tonyh said...

Hope you are not too frustrated with the project - you have made loads of progress! Once the walls are skimmed you will see an amazing transformation really quickly. Keep up the good work!

Torie of Victoria & Florence said...

from your post it sounded like it really was 2 steps forward and 4 steps back but the pictures in the next post suggest otherwise .... it looks like a house!
I can't wait to see it in a couple of weeks by which time it'll have come on leaps and bounds I'm sure